milestones
 
Status of Milestones
 

Sr. No.

Description of Milestone

Target date

Status  as on 31.07.10

1

Cumulative Heading excavation of HRT length of 2515 m from six faces.

31.03.11 1092m since 1.04.2010

2

Cumulative concrete lining of HRT length of 2926 m from two faces 31.03.11 1392 m since 1.04.2010

3

Completion of widening of surge shaft 30.06.10 Excellent target achieved. As per revised design widening depth was increased by 21 m i.e. up to 149.50m depth has been completed on 30.07.10. 

4

Completion of excavation of underground pressure shaft 3 no. 30.09.10 Cumulative completed 598m out of 649m. 2 Shafts completed, 1 in progress. 

5

Erection and commissioning of EOT crane in Service Bay

30.09.10

In Service Bay 1, erection is in progress and Sole plates have been fixed. 
Service Bay 2 is ready for fixing of Sole Plates.

 

   