Choose Language:   Hindi  |  English
 
SEARCH

 

You do not have flash player installed.
Click Here to install latest Flash Player.

Home  -  Projects  -  Rampur Project  -  Introduction
 
   Introduction
  Salient Features
  Financing Details
  Important Events
  Progress Report
  Milestones
 
Nathpa Jhakri HEP
Rampur HEP
Luhri HEP
Devsari HEP
Naitwar Mori HEP
Jakhol Sankri HEP
Arun III HEP
Dhaulasidh HEP
Wangchu HEP
Kholongchu HEP
 
introduction back
Rampur Hydro-electric Project (412 MW) is located downstream of already executed 6 x 250 MW NJHEP and intends to use the desilted water discharge by the upstream project. As such the construction of Rampur HEP does not involve construction of any dam / desilting chambers and thus avoiding any serious environmental impact on local flora and fauna. It is proposed, to divert water from out-fall arrangement of NJHEP through a 10.5 mtr. Dia HRT of 15.088 kms. Length. The construction of the project involves in addition to the Head Race Tunnel a 155.75 mtr. High and 38 mtr. dia surge shaft, 3 numbers of pressure shafts/penstocks of 5.4 m/3.8 m dia each and a surface Power House.

Memorandum of Understanding (MOU) was signed on 20th oct. 2004 with the Government of H.P. The Stage-I and Stage-II activities have almost completed. The Govt. of India has accorded Cabinet Committee on Economic Affairs (CCEA) clearance to Rampur HEP on January 25, 2007, subsequent to which the major civil works of Rampur HEP were awarded on February 1, 2007 and Electromechanical works were awarded on september 16, 2008.

The Company has adequate inhouse expertise and skill to execute this project. On account of Power shortage in the northern grid to which the power to be generated shall be fed, the Company does not foresee any difficulty in selling the power. The Company seeks thru this presentation to invite in-principle willingness and indicative terms & conditions for raising debt funds to complete the project.

Rampur HE Project has added one more feather in its cap to become the first Hydro Electric Project in India to obtain ISO 14001 & IS 18001 for Environment Management System and Occupational Health & Safety Management System respectively at execution stage in a remarkable shortest spell of four months.

PROJECT COMPLETION SCHEDULE
The Project is schedule to be completed in a period of 60 months from the date of sanction by Government of India, as detailed below :

Unit-1  :  55 months
Unit-2  :  56 months
Unit-3  :  57 months
Unit-4  :  58 months
Unit-5  :  59 months
Unit-6    :    60 months

ENVIRONMENTAL MEASURES
SJVN will take necessary action to comply with the environmental safeguards stipulated by Ministry of Environment & Forests ( MoEF ) in its clearance letter dated March 31, 2006. These will include afforestation programme, catchment area treatment, biodiversity conservation plan, green belt and landscaping restoration of dumping areas, control of air and noise pollution, muck disposal, sewage and solid waste management, fisheries development, fuel arrangements, disaster management and environmental monitoring programme.

REHABILITATION & RESETTLEMENT
28 no families shall be displaced due to acquisition of their land for Project construction. The rehabilitation package for the displaced persons shall be implemented as per the Government of India guidelines in practice. Resettlement & Rehabilitation Scheme for Project Affected Families ( PAFs ) of Rampur HEP has been agreed between SJVNL and GOHP in the Implementation Agreement signed on October 20, 2004. All out efforts shall be made by SJVNL to ensure the early rehabilitation.
 

   

Copyright © 2007 | Visitor Number:808262
All rights reserved with SJVN Limited