Sr. No. |
Description of Milestone |
Target date |
Status upto 31.07.10 |
|
1. |
Award of work of Bridges from Dam to Kenu
Adit and from PH to Shotara Adit |
31.03.11 |
Estimates for all 10 no. bridges have been prepared, 9 No. technically sanctioned, balance 1 no. has been provided in PP & M department and stand submitted to Cometent Authority for approval.
Bidding documents have been prepared and got vetted from the Corporate Contarct Deptt. necessary tendering process to award the work by due date shall be initiated. |
|
2 |
Construction of 275 m drift at Sush Adit |
31.03.11 |
Work awarded on 23.04.2010.Work stopped by the Forest/divisional Water Shed Officer on the plea that exploratory drifts are not covered under Forest conservation Act 1980. On 27.07.10 the agency has intimated to start the work immediately as issue with the Forest Department has been sorted out. First blast took place on 29.07.10. |
|
3 |
Diversion of Forest/Govt. Land from MOEF and acquisition of Private Land |
31.03.11 |
For diversion of Forest land PCCF, Shimla has submitted the case to GoHP on 29.06.10 for onward transmission to MOEF, GOI. Addl. Chief Secretary (Forest) has sought some clarifications. Matter being persued.
Private Land:
Distt Shimla-
i) Total cases- 20
ii) Notified under Section -IV- 17
iii) Public hearing held under Section- V- 16
iv) Cases sent to GoHP for notification under section VI & VII-16
v) Cases sent for notification under section VI & VII-12
Distt. Kullu-
i) Total cases- 03
ii) Notified under Section -IV- 03
iii) Public hearing held under Section- V- 01
Distt. Mandi-
i) Total cases- 04
ii) Notified under Section -IV- 04
iii) Public hearing held under Section- V- 02
iv) Cases sent to GoHP for notification under section VI & VII-02
v) Cases sent for notification under section VI & VII-01 |
|
4 |
TEC of DPR of LHEP (775 MW) from CEA |
31.03.11 |
CEA has cleared the chapters on Geology, water availability and diversion flood. Reply to observations sent to CEA on 30.07.10. |
|
5 |
Completion of Social Impact Assessment Studies |
31.07.10 |
Draft report received on 21.07.10 and is under examination. |
|
6 |
Office Complex at Power House: Award of work |
31.03.11 |
Principal approval of site received on 29.06.10.
Concept drawings issued by Architect Cell. Tender Drawings awaited. |